| a. |
Construction of godowns, plinths, ancillary buildings, roads and Railway sidings. |
| b. |
Requirement of storage capacity are to be ascertained by Distt. Offices and submitted to Regional office. |
| c. |
Availability of land available in own complexes or to be acquired / purchased. |
| d. |
Requirements along with preliminary estimates are submitted to Zonal Office (N) /Head Quarter for approval. |
| e. |
Availability of funds and accord of A.A & E. S by the competent authority as per D.O. P .
|
| f. |
Detailed estimates to be prepared and submitted to the competent authority for accord of Technical sanction and approval of DNIT as per D.O.P. |
| g. |
Call of tenders after wide publicity through Newspapers, Internet, opening of tenders and their processing of tenders for award of work by competent authority as per D.O.P. |
| h. |
Execution of works as per contract conditions and specifications. |
| i. |
Quality of works also checked by visiting Engineers viz.AGM (CE) /DGM (CE) GM (Engg.)/ED (Engg). |
| j. |
Preparation of running account bill for payment of work done by the contractor. |
| k. |
After completion of works, the works are inspected by the competent authority as per D.O.P and the completion certificate is recorded in the measurement book. |
| l. |
Handing over of capacity for storage |
| m. |
Preparation of final for payment to the contractor. |